First Three-Month Milestone of Trouble-Free Dragon 12 Testing Reached

Ocean energy developer, Minesto, announced that for three months, since its initial installation in February 2024, the tidal kite Dragon 12 has been successfully grid connected and delivers as expected at the site in Vestmanna.
First Three-Month Milestone of Trouble-Free Dragon 12 Testing Reached
Courtesy of Minesto

In addition, for the first time, an array of tidal kites is in operation – the 1.2 MW D12 and one 100kW D4, adding valuable production data for array build-out. The data being generated underlines commercial readiness of Dragon Class systems and the continued testing supports both critical sales activities and preparations for product delivery.

Early February 2024, the 1.2 MW powerplant – Dragon 12 – was successfully installed and commissioned at the site in Vestmanna, Faroe Islands. This has resulted in an ongoing three-month period of testing and electricity production, generating valuable results and data to underline commercial readiness of Dragon Class technology at commercial scale.

Notably, real test data from the commercial scale D12 is now available to customers and is used to show autonomous functionality, product performance, and service interval analysis.

"With the generated test data at hand, we can now conclude that Dragon Class is ready for batch production to bring the first tidal energy arrays to life," said Dr. Martin Edlund, CEO of Minesto.

Moreover, the large Dragon 12 (1.2 MW) is accompanied by a smaller Dragon 4 (100kW) in the Vestmanna strait, which means that two systems are installed and grid-connected in parallel. The world's first mini array of tidal energy kites is in operation.

Operating two systems in parallel contributes to new ways of verification and learning in core areas, such as kite-park design, product range modularity and performance optimization.

Minesto plans to continue electricity production and testing as an integral part of the ongoing commercial roll-out agenda. The purpose of the continued testing is three-fold: continue to demonstrate the competitive advantage of Dragon class technology, secure capability to deliver commercially viable products, and push performance to further expand the exploitable market.

"It is both satisfactory and vital to see that the February installation of Dragon 12 has resulted in a three-month period of successful production testing," said Edlund.

 

Related Stories

Minesto Welcomes Cooperation Between EU and Faroe Islands

Minesto Evolves its Faroese Business Case, Upgrading to 200 MW Tidal Energy Buildout

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).