Guillena is one of two assets located in southern Spain which belongs to the Greco portfolio, acquired in March 2022. The other asset, Jaén was the first asset within the Greco portfolio to finish construction and has been operational since November 2022.
Following completion of Guillena, the Company's portfolio is now fully operational and the operating capacity has increased to approximately 464 MW.
AER has also announced that the takeover of the Norwegian “Rock” wind farm, under an Engineering, Procurement and Construction Management (EPCM) agreement has now been achieved. The Rock has been operational since November 2022 following completion of the Turbine Supply Agreement, whilst final completion would be declared once takeover under EPCM agreement has happened.
Eolus will remain responsible for the upcoming appraisal case with the Sami district, which is due to commence on 30 May 2023.