pv

Spain

Ingeteam commissions the first PV plant with batteries in Spain

The 40 MW Arañuelo III photovoltaic plant is the first large-scale PV plant in Spain to incorporate an energy storage system, consisting of, in this case a 3 MW/9 MWh battery system.
Ingeteam commissions the first PV plant with batteries in Spain
Courtesy of Ingeteam

The solar plant is now operational and is part of the Campo Arañuelo photovoltaic complex developed by Iberdrola in the district of Almaraz in Extremadura, formed by the Arañuelo I, II and III solar plants, with a total installed capacity of 143 MW.

Ingeteam was selected by Iberdrola to equip the Campo Arañuelo solar complex. In the case of Arañuelo plants I and II, Ingeteam supplied the usual components for a PV plant, consisting of PV inverters, transformer stations, PPC (power plant controller) system and commissioning. The novelty of the project relates to Arañuelo III, in that, in addition to all the above, Ingeteam also completed the turnkey supply of the energy storage system. In other words, Ingeteam supplied the lithium-ion batteries, the integration of the batteries in the 45-foot containers, the converters, the SCADA monitoring system, the civil work, the field assembly of the storage system and its subsequent commissioning.

Furthermore, Ingeteam was also responsible for the supply of the digital protection and control system for the Arañuelo III substation. The scope of supply included the systems responsible for the protection and control of the line delivering power to the grid from the plant, the 30/132kV step-up transformer, the collector circuits and the connection circuit for the energy storage system, providing the renewable energy control centre (CORE) with real-time information and access to any of the elements.

As well as being the first large-scale solar plant in Spain to incorporate batteries, this project offers a further novel feature with the inclusion of the battery storage system within the PV plant as a distributed system with a DC-Coupling configuration. In this mode, the batteries are installed within the solar array and the battery converters share the DC connection with the PV inverters, offering the following key technical advantages:

The possibility of utilising the extra power from the solar panels that is not used during peak production hours (Clipping Recapture).

This makes it possible to minimise the losses by charging the batteries from the PV array, given that the connection between the panels and the batteries only passes through the DC/DC converter. The discharge is also more efficient, due to the fact that no power transformer is required, in contrast to the AC connected solution.

This novel technique to create a hybrid PV generation system with battery energy storage, was made possible thanks to the development by Ingeteam of a new battery converter: the DC-DC series of the INGECON SUN STORAGE Power family. This converter is coupled to the DC input of a PV inverter, thereby obtaining in practice a hybrid central inverter with a direct coupling to the solar panels and batteries alike and with a single AC output that is coupled to the LV/MV transformer.

Ingeteam’s supply for the Campo Arañuelo PV complex consisted of the following:

29 power stations fitted with all the necessary equipment to inject medium voltage power: LV/MV transformer, medium voltage switchgear, auxiliary services transformer and auxiliary services switchgear.

72 units of the INGECON SUN 1640TL B630 solar inverter with a rated power output of 1.64 MW.

Two units of the INGECON SUN STORAGE Power DC-DC battery inverter with a rated power output of 1.5 MW, for Arañuelo III.

Two 45-foot, fully integrated battery containers, each for 1.5MW/4.5MWh, for Arañuelo III.

Three INGECON SUN Plant Controller systems.

Hybrid plant controller (solar + batteries) for Arañuelo III.

SCADA monitoring system for Arañuelo III.

Civil work and assembly of the storage system at Arañuelo III.

Commissioning of the three photovoltaic plants and also the storage system at Arañuelo III.

Digital system for the control and protection of the Arañuelo III substation.

For additional information:

Ingeteam

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).