RWE Starts Construction Of Battery Storage Projects With Combined Capacity Of 450 MW

RWE, a renewable energy company, continues to grow its green energy portfolio in the U.S. at a record pace. The company broke ground on three battery energy storage systems in Texas, bringing RWE’s total battery storage projects under construction to 931 megawatts across California, Texas and Arizona. 
RWE Starts Construction Of Battery Storage Projects With Combined Capacity Of 450 MW
Courtesy of RWE

Onsite construction is now underway at RWE’s Crowned Heron 1 and Crowned Heron 2 and Cartwheel 1  BESS projects in Texas. The three assets will have a total power capacity of 450MW and storage capacity of 900 megawatt-hours (MWh), contributing toward the company’s global growth target for battery storage of 6 GW by 2030.

Once operational, RWE’s Crowned Heron 1 and 2 and Cartwheel BESS will provide critical energy storage capacity to support the stability and resilience of the Electric Reliability Council of Texas (ERCOT) grid, especially as the state continues to deal with record-breaking peak power demand during extreme heat events. 

Hanson Wood, Head of Development, Utility-Scale Renewables for RWE Clean Energy, said, “These battery storage projects mark a significant step in our ongoing commitment to enhancing the energy infrastructure in Texas, while growing our energy storage portfolio. When completed and operating, our Crowned Heron 1 and 2 and Cartwheel battery projects will serve as reliable energy storage solutions to enhance grid stability and support the state’s rapidly growing renewables sector.”

Crowned Heron 1 and Crowned Heron 2 are both 150 MW (300 MWh) BESS projects located in Fort Bend County, Texas. Construction of Crowned Heron 1 is expected to be completed in summer of 2025, with Crowned Heron 2 commissioning planned for fall of 2025.

Cartwheel is a 150 MW (300 MWh) BESS project located in Sulphur Springs, Texas, where RWE also operates Bright Arrow, a 300 MW solar and 100 MW (200 MWh) project announced earlier this year. Construction of the Cartwheel project is expected to be completed in the summer of 2025.

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).