With a planned capacity of 50+ megawatts (MW) and 400+ megawatt hours (MWh), the Limondale BESS will support the energy transition by storing excess renewable energy and feeding it into the NSW grid when it is needed most. The project will be located next to RWE’s 249 MWac Limondale Solar Farm – which is one of Australia’s largest. The BESS will connect to existing grid infrastructure.
Tesla has been selected as the BESS supplier, and Beon Energy Solutions as the delivery partner for the Balance of Plant, which includes the civil, structural, electrical and control works required to connect the Megapack to the existing 33kV substation. Construction is scheduled to start in the second half of this year, with commissioning planned for late 2025.
Katja Wünschel, CEO RWE Renewables Europe & Australia, said, “RWE’s investment decision and signing of supplier contracts for the Limondale BESS project is an exciting step forward in our commitment to the Australian renewables sector and support of New South Wales’ renewable energy ambitions."