Biden Administration Approves Nation’s First Major Offshore Wind Farm

Secretary of the Interior Deb Haaland and Secretary of Commerce Gina Raimondo today announced approval of the construction and operation of the Vineyard Wind project — the first large-scale, offshore wind project in the United States. The Secretaries were joined by labor leaders who have been working to ensure that the project is built and maintained by union labor.
Biden Administration Approves Nation’s First Major Offshore Wind Farm

The 800-megawatt Vineyard Wind energy project will contribute to the Biden-Harris administration’s goal of generating 30 gigawatts of energy from offshore wind by 2030. The project will be located approximately 12 nautical miles offshore Martha's Vineyard and 12 nautical miles offshore Nantucket in the northern portion of Vineyard Wind’s lease area. It will create 3,600 jobs and provide enough power for 400,000 homes and businesses.

The 800 MW Vineyard Wind project will utilize 62 GE Haliade-X turbines, currently the world’s most powerful turbine with a capacity of 13 MW per machine utilizing wind blades spanning 107 meters. In November 2019, GE shipped a 107 meter Haliade-X blade to the Wind Technology Testing Center – the only facility of its kind in North America – for stress and durability testing that validated the technology can withstand more than 25 years of operation at sea, a key part of the technology development process.

“A clean energy future is within our grasp in the United States. The approval of this project is an important step toward advancing the Administration's goals to create good-paying union jobs while combatting climate change and powering our nation,” said Secretary of the Interior Deb Haaland. “Today is one of many actions we are determined to take to open the doors of economic opportunity to more Americans.”

“Today’s offshore wind project announcement demonstrates that we can fight the climate crisis, while creating high-paying jobs and strengthening our competitiveness at home and abroad,” said Secretary of Commerce Gina Raimondo. “This project is an example of the investments we need to achieve the Biden-Harris administration’s ambitious climate goals, and I’m proud to be part of the team leading the charge on offshore wind.” 

In its first four months, the Biden-Harris administration has catalyzed the offshore wind industry by announcing the first ever national offshore wind energy mandate, creating a roadmap for the future of this innovative industry. Achieving the 30 gigawatt goal is anticipated to result in the creation of tens of thousands of living wage, family-supporting union jobs while positioning America to lead a clean energy revolution and tackle the climate crisis. Building the offshore wind supply chain can feed steel mills in West Virginia, support ship building in Texas, and wind turbine manufacturing in both inland areas and on the coasts.

“On behalf of the Massachusetts Clean Energy Center, I would like to congratulate Lars Pedersen and the entire Vineyard Wind team for today’s major milestone,” said Steve Pike, CEO of MassCEC. “We look forward to hosting Vineyard Wind at the New Bedford Marine Commerce Terminal and continuing our mutual efforts to advance workforce and supply chain development as well as science, research and innovation for the Nation’s first commercial offshore wind farm.”

Today’s Record of Decision (ROD) grants Vineyard Wind final federal approval to install 84 or fewer turbines off Massachusetts as part of an 800-megawatt offshore wind energy facility. The project is expected to create 3,600 area jobs and will power up to 400,000 homes. Turbines will be installed in an east-west orientation, and all the turbines will have a minimum spacing of 1 nautical mile between them in the north-south and east-west directions, consistent with the U.S. Coast Guard recommendations in the Final Massachusetts and Rhode Island Port Access Route Study.

The ROD adopts mitigation measures to help avoid, minimize, reduce, or eliminate adverse environmental effects that could result from the construction and operation of the proposed project. These mitigation, monitoring, and reporting requirements were developed through input, consultation, and coordination with stakeholders, Tribes, and federal and state agencies. For more information, please see appendix A of the ROD.

“This project represents the power of a government-wide approach to offshore wind permitting, taking stakeholder ideas and concerns into consideration every step of the way,” said Bureau of Ocean Energy Management Director Amanda Lefton. “We will continue to advance new projects that will incorporate lessons learned from analyzing this project to ensure an efficient and predictable process for industry and stakeholders.”

The ROD is jointly signed by and addresses permitting decisions by BOEM, U.S. Army Corps of Engineers, and the National Marine Fisheries Service within the National Oceanic and Atmospheric Administration.

Prior to construction, Vineyard Wind must submit a facility design report and a fabrication and installation report. These engineering and technical reports provide specific details for how the facility will be fabricated and installed in accordance with the approved Construction and Operations Plan.

To ensure that the project is developed in an environmentally responsible manner that protects and preserves marine wildlife, including the critically endangered North American Right Whale, Vineyard Wind will invest millions of dollars to develop and deploy innovative technologies and undertake scientific research to further safeguard marine mammals; institute comprehensive monitoring protocols to ensure that construction doesn’t take place when right whales are near the lease area; utilize acoustic monitoring technology throughout construction including in transit corridors, and employ trained protective species observers to spot right whales visually during transit and foundation installation.

“With the increasing threat of climate change, responsibly sited and operated clean energy projects like Vineyard Wind are critical to the survival of birds,” said Garry George, director of the National Audubon Society’s Clean Energy Initiative. “Even with this approval we expect to continue working with Vineyard Wind to help meet its commitments to avoid, minimize, and mitigate and monitor the project’s impact on the environment.”

In addition to today’s announcement, since January 20, the Department has initiated the environmental review of two other offshore wind projects, and pursued additional leasing opportunities in the New York Bight.

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).