wind

DEME Offshore LNG vessel successfully installs DolWin6 HVDC cable

DEME Offshore has successfully installed the DolWin6 High Voltage DC (HVDC) cable in the North Sea deploying its DP3 vessel ‘Living Stone’ – the first time a cable laying vessel has installed cables while powered on LNG, dramatically reducing emissions.
DEME Offshore LNG vessel successfully installs DolWin6 HVDC cable
Courtesy of DEME Group

‘Living Stone’ picked up the cables directly from the Nexans manufacturing facility in Halden, Norway at the beginning of June and transported them to the offshore site in the German Bight. The vessel has two turntables making it ideally suited for installing bundled HVDC cables. The HVDC cable pair was bundled together with the fibre optic cable on board ‘Living Stone’ and seamlessly installed.

DolWin6 has a transmission capacity of 900 MW and is owned and operated by transmission system operator TenneT. The HVDC cable runs from several offshore wind farms in Germany via Norderney to German mainland.

“We are pleased to see another campaign successfully concluded by our cable installation vessel ‘Living Stone’” said Bart de Poorter, General Manager DEME Offshore Renewables. “Carrying out the project on LNG is another major milestone, highlighting once more the unrivalled technical capabilities of ‘Living Stone’ and its crew.”

For additional information:

DEME Offshore

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).