wind

DNV embarks on project to support plan to bring zero-carbon offshore wind power to South Korea

Independent energy expert and assurance provider DNV is assisting KEPCO (Korea Electric Power Corporation) Research Institute in the development of a long-term offshore power grid plan to deliver renewable offshore wind power to South Korea, with completion scheduled for mid-2025. As technical advisor, DNV will develop a conceptual design and routing plan to enable the technically and economically optimal integration of large-scale offshore wind to the grid.
DNV embarks on project to support plan to bring zero-carbon offshore wind power to South Korea
Offshore wind farm at Port of Noshiro, Japan. Courtesy Wikimedia Commons.

Suitable analysis models of offshore network systems will be proposed in order to investigate the optimal topology and design standards for the offshore system.

South Korea has set a goal of deriving 20 percent of its power from renewable sources by 2030, and wind energy is a rapidly growing industry, supported by the policy ambition to grow the wind share of the country’s energy mix from 1 percent in 2015 to 6 percent by 2030 and various measures – including tax incentives.

In February 2021, the government presented an 8.2 GW and KRW48.5 trillion ($43.2 billion) mega-project that, when completed in 2030, should become the world’s largest single offshore development. However, grid integration has to be worked on in parallel.

KEPCO aims to expand its network along the western coast of South Korea and deliver power from high capacity renewable Offshore Wind Farm (OWF) sites to key demand centres in the country’s capital, Seoul. The city houses around 10 million people, and nearly 26 million, half the country’s population, live in the greater Seoul area, which is also the country’s main industrial location.

DNV will develop system analysis models to study the design specification and optimal topology for gigawatt (GW) scale high-voltage direct current (HVDC) linkage technology to improve system acceptability and transferring capacity from OWF projects in the southwestern coast of the country. DNV will also estimate the costs of the proposed optimal integration plan to minimise the total investment needed for integrating OWFs into the onshore power grid.

DNV’s detailed work scope includes collecting and analysing offshore wind farm data; preparing a conceptual design of the power collecting element (bus) for the OWF; drafting functional specifications for AC/DC converter stations; analysing the impact of the offshore DC system to the onshore AC system; reviewing the relevant environmental and code limitations for the network routing and delivering a detailed design of the multi-terminal DC system including the converter topology, location and control/operational strategy.

“The KEPCO HVDC Research project is increasing our expertise and experience in this growing market segment in South Korea” said Dr. Yang Byeong Mo, DNV’s project manager. “It has taken a year of detailed discussion with KEPCO to define and secure the work. The project scope requires close cooperation with our European power grids team, which will lead to technology improvements and boost local knowledge on renewables-grid integration in South Korea.”

DNV has positioned itself as a go-to partner in the area of offshore transmission network planning in North-western Europe and North America, particularly when HVDC technology is involved. Globally, an increasing number of offshore wind projects utilising HVDC technology have been implemented or are being planned.

Brice le Gallo, DNV’s Vice President and Regional Director, Energy Systems for Asia Pacific, added that the Asia Pacific market is showing increasing interest in HVDC technology with the wave of renewable energy generation including offshore wind set to drive the region’s energy transition and that the project will add to DNV’s considerable and growing experience in the region’s energy transformation, with the hope that it will lead to more collaboration in the future.

For additional information:

DNV

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).