K2 Management calls for better alignment in offshore wind project timelines and equipment lifecycles

Limitations on wind turbine design lifetimes are hampering efforts to manage costs in asset lifecycles, reducing the effectiveness of long-term decision making and disrupting the effectiveness of offshore wind energy in low carbon power generation says clean energy consultancy K2 Management.
K2 Management calls for better alignment in offshore wind project timelines and equipment lifecycles
Courtesy of NREL

New Wind Europe figures indicate that in the next five years, 38 GW of European wind farms will reach 20 years of operations, and therefore require decisions to be made around repowering, life extension or full decommissioning. Owners of older nearshore offshore wind farms in particular will find it impossible to repower these sites with larger, more efficient turbines.

Yet, as demonstrated across early offshore wind projects including North Hoyle, Scroby Sands, Kentish Flats, Barrow, and Beatrice, realistic lifespans beyond 35 years are achievable using current asset management methodologies and O&M activity.

K2 Management is therefore calling on the offshore wind industry to be better aligned in project timelines and equipment lifecycles, particularly as the latest offshore wind leasing rounds propose a 60-year project lifespan, almost three-times the approved turbine design lifetime.

“In recent years there has been an emphasis on OEM’s developing and proving the commercial viability of bigger and more efficient turbines, targeting a lower LCoE that makes offshore wind more competitive than traditional offshore energy” said Gary Bills, Regional Director EMEA, K2 Management. “At the 20 to 25-year mark, however, an offshore wind farm owner’s mind should be on how their project can continue to efficiently and profitably support decarbonisation goals and make the most of their lease as a possible alternative to the financial and technical hurdles of retrofitting the latest, largest machines to existing infrastructure. Ultimately, decision making on lifetime extension must be made far earlier in the project lifecycle.  Each offshore wind development has very specific requirements, so looking at each element – such as turbine performance over time or improvements in resource assessment – much earlier in the project’s lifecycle will be key to arriving at the best investment decision, before external pressures limit alternative options.”

K2 Management delivers complex engineering, planning, project management, and due diligence services across the full project value chain.

For additional information:

K2 Management

Baterías con premio en la gran feria europea del almacenamiento de energía
El jurado de la feria ees (la gran feria europea de las baterías y los sistemas acumuladores de energía) ya ha seleccionado los productos y soluciones innovadoras que aspiran, como finalistas, al gran premio ees 2021. Independientemente de cuál o cuáles sean las candidaturas ganadoras, la sola inclusión en este exquisito grupo VIP constituye todo un éxito para las empresas. A continuación, los diez finalistas 2021 de los ees Award (ees es una de las cuatro ferias que integran el gran evento anual europeo del sector de la energía, The smarter E).