The project will feature 18 V150-4.5 MW which Vestas will supply and install. Upon completion, Vestas will also deliver a 20-year Active Output Management 5000 (AOM 5000) service agreement. This agreement will optimise energy production while also providing long-term business case certainty.
The El Llano wind complex will provide renewable electricity for Aluar’s aluminium smelting facilities in Puerto Madryn, the largest in the country and will help Aluar meet the requirement from the Argentinian authorities for large electricity consumers to get a percentage of their consumption from renewable sources.
“Vestas is pleased to grow our partnership with Aluar, one of the largest aluminium smelters in South America, who, as Vestas, has a strong commitment to Argentina’s energy transition” said Andrés Gismondi, Sales Senior Director for Vestas LATAM South Cone. “This order materialises the third expansion of the El Llano wind complex that will soon have a total of 246 MW of sustainable energy coming from Vestas´s turbines to power Aluar’s aluminium smelting facilities in Puerto Madryn. This underlines how Vestas´ solutions can support energy-intensive industries to accelerate their energy transition by powering their operations with cost-efficient and sustainable energy”.
Turbine delivery is planned for the fourth quarter of 2022, whilst commissioning is expected for the third quarter of 2023.
For additional information: